How to change the project manager on a project at all WBS levels?
KB Article #:
62452
Summary:
How to change the project manager on a project at all WBS levels?
Description:
How to change the project manager at all WBS levels?

Resolution:

Make a backup of the data before following these steps.

Go to Utilities>Advanced Utilities>Search and Replace

  1. Input a Description  
  2. Application Area = Projects  
  3. Select Records = choose the specific project involved 
  4. WBS Level = pick the appropriate level(s)  
  5. Column to Update = PR.ProjMgr (or custom field if that's the case).  
  6. Update Method = Value  
  7. Input the new project managers employee id as the new value.  
  8. Click Run in the tool bar to process this change.  
 